Grid-Scale Energy Storage
Since 2019, S4 Energy has been providing flexibility services to Dutch grid operators.
In Almelo, we stabilize the regional electricity grid through a 10MW connection. Increasing battery energy storage capacity from 10MWh to 40MW
S4 has been responsible for the full cycle from early development, EPC to commissioning and offers flexibility services to date.
Photos of this project
Commissioning date
23-05-2019
Owner of the project
S4 Energy
Province
Overijssel
Power in kW
10 MW