Green Energy Storage (GES) officially commissioned the battery energy storage system (BESS) at Bomhofsplas in Zwolle.
A BESS (Battery Energy Storage System) is a large-scale battery energy storage system that temporarily stores electricity and later releases it to the grid. In doing so, it balances the supply and demand for power, supports the stability of the power grid and allows more renewable energy such as solar and wind power to be used efficiently.
This milestone will make additional flexibility available on the Dutch power grid, allowing more renewable energy to be integrated and alleviating grid congestion.
Strong link between solar and storage
The system has a capacity of 11MW and a storage capacity of 22MWh. Thanks to its direct connection to the floating solar farm Bomhofsplas (27 MWp, operational since 2020), locally generated solar power can be efficiently stored and deployed later when electricity demand is highest. The battery provides services such as balancing, congestion management and grid stability. Thus, the project contributes directly to a safer, more efficient and more sustainable operation of the Dutch energy system.
Cooperation between strong partners
The project is an initiative of Green Energy Storage (GES) and was realized in cooperation with:
- Energiefonds Overijssel (EFO).
- Greenchoice
- Dekker Group
- Privatis (electrical installations and integration)
- Blue Finger Energy
From idea to operation in one year
The project is distinguished not only by the unique coupling of a battery to a floating solar park on an active sand mining site, but also by its exceptionally short lead time:
- October 2024 - Financial close completed
- December 2024 - Start of construction
- April 2025 - Supply battery containers
- June 2025 - Connection to existing grid connection and solar farm
- August 2025 - Performance tests and joint control of solar farm + battery
- September 2025 - Official commissioning of EOS Bomhofsplas
Within just twelve months of its financial completion, the battery was made operational, a testament to decisive collaboration
Commissioning date
09-10-2025
Owner of the project
Green Energy Storage (GES)
Province
Overijssel
Power in kW
11MW
Capacity in kWh
22MWh