Moerdijk BESS
RWE’s first inertia-ready battery energy storage system (BESS) has started commercial operation on the site of the company’s power plant in Moerdijk, the Netherlands. It is the first of its kind in operation in the Central European grid.
The BESS has an installed capacity of 7.5-megawatts (MW) and a storage capacity of 11 megawatt hours (MWh). Highly responsive control technology and inverters with grid-forming functionality enable the system to supply or absorb power within milliseconds, helping to stabilise the power grid. This service is called inertia.
Foto's van dit project
Datum in gebruikname
16-06-2025
Provincie
Noord-Brabant
Vermogen in kW
7.5 MW
Capaciteit in kWh
11 MWH